Sewer Project Won’t Affect Fireworks/Air Show

Beginning Saturday, the Fengler Street overpass will be closed for work related to the Kerper Blvd. sanitary sewer reconstruction project. Dubuque City Engineer Gus Psihoyos says the Fengler project is scheduled for completion on June 29th. The sanitary sewer reconstruction project should be almost done at about the same time and Psihoyos says it shouldn’t have any effect on travel for one of Dubuque’s biggest events of the year. The Fengler project was slated to start on May 28th, but because of inclement weather and high water levels, it had to be delayed until now.